As readers of this blog know I have been opposed to the idea of a temporary modular building (trailer) as our west branch library in Heroes Park. I and many, many residents of the Yucca district consider this an insult, as if that is all that we deserve after waiting 18 years.

After the city council acceptance of the Canvass of Votes I was invited to meet on October 7, 2016, with appropriate city personnel regarding the plans for this library. I had requested a meeting after it came to my attention that approximately $2 million dollars would be available for its construction and it appeared that the cost to build a permanent, phase I of a brick ‘n’ mortar branch library would be virtually the same as the cost of a modular building. My meeting with city staff confirmed that $2 million dollars would be sufficient for either a brick & mortar building or a modular building.

Based upon that information and learning that the next step would be to secure city council approval to move forward with the design, I requested that the design process incorporate plans for a permanent brick & mortar building as well as the modular design. The modular design had been directed by city council in a previous action.

I was successful in getting the design for a permanent brick & mortar included in the proposed city council action and on December 20, 2016, city council authorized the City Manager to enter into a Professional Services Agreement with Dick and Fritsche Design Group, Inc. (DFDG) to provide design and architectural drawings for the potential Heroes Branch Library, within Heroes Regional Park located at West Bethany Home Road and North 83rd Avenue, in an amount not to exceed $410,090. Here is the link to that city council meeting: http://glendale-az.granicus.com/MediaPlayer.php?view_id=2&clip_id=2597&meta_id=55164 .

Below is the schedule of work.  As can be seen, it will be 9 months to create the design and construction documents. Although that seems to be very slow, in city terms, it is fast and being expedited. I will monitor the progress of the various steps to make sure the timeline remains intact. The next milestone will be for city council to award a construction contract to build in approximately September of 2017. I will continue to advocate for and seek acceptance from council for the permanent brick & mortar west branch library building. Knowing that the costs are virtually the same for either type of building it would make economic sense that a permanent structure be built with the capacity for future expansion. The library itself will be completed and open for business approximately August of 2018.

·       Notice to Proceed                                                                        1/2/17  

·       Program Verification – Site Analysis                                          1/2/17-1/13/17 (2 weeks)

·       Schematic Design                                                                         1/16/17-2/24/17 (6 weeks)

·       Design Development                                                                   2/27/17-4/21/17 (8 weeks)

·       Construction Documents                                                            3/1/17-3/31/17, 4/24/17-6/16/17

                                                                                                                (8 wks.)

·       Plan Review and Permit / Prepare Bid Docs.                            6/19/17-8/11/17   (8 weeks)

·       Bid                                                                                                    8/14/17-9/8/17 (4 weeks)

·       Notice to Proceed                                                                         9/11/17-10/20/17   (6 weeks)

·       Council Award                                                                                10/12/17 

·       Construction                                                                                   10/23/17-7/27/18 (40 weeks)

·       Close out – Occupy                                                                         7/30/18-8/24/18 (4 weeks)

·       Final Acceptance                                                                            8/27/18

I will also continue to advocate for additional elements of Heroes Park, also long overdue. Nearly every district has its points of pride from the Foothills Library and Foothills Recreation & Aquatic Center, to Sahuaro Ranch, to Thunderbird Paseo Racquet Center, to Murphy Park and the Civic Center. It’s time for west Glendale to have its major amenity and its point of pride completed.

© Joyce Clark, 2016        

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.