First a little history. Twenty years ago, in 1998, what is today known as Heroes Park first appeared in the city’s Capital Improvement Program (CIP). Today Heroes Park remains unfinished…after 20 years of waiting. Residents who bought in this area expected its timely completion. Instead they raised a generation of children without the benefit of this quality of life amenity, especially a library.  Now they have grandchildren whom they hope will be able to enjoy a completed park before they too become adults with their own children.

Heroes Park Concept Plan. Items depicted in yellow are completed. All others have not.

One of the planned components of the park has always been a West Branch Library. Again, more history. The former mayor (Scruggs) used every ploy to deny funding for the library and park completion. She and I butted heads on virtually every issue and she was not about to give the person (whose nickname for me was “Evil”) any kind of victory – especially a park, rec center and library. Her most infamous raid occurred in 2006 when she and her “mushrooms” (the gang of four whom always did her bidding) diverted $6 million dollars from library construction and allocated it to the construction of the Glendale Public Safety Training facility (GRPSTC). The result being funding for library construction vanished in an instant.

When the great recession occurred every possible residential amenity was cut from the CIP including completion of Heroes park, rec center and library. These were not the only amenities to get the axe. Library hours were cut and many youth recreation programs disappeared or were severely diminished. O’Neil Pool in the Ocotillo district (formerly part of my district, the Yucca district) received no funding during that period after it was closed due to the need for major repairs. To this day it remains closed and in need of significant funding to repair or replace it. It is a disgrace.

Over the past 20 years south and west Glendale often were ignored when it came to allocating city funding for amenities with one exception – Rose Lane Aquatic Center, in the Ocotillo district, was constructed. To this day it is heavily used by an economically challenged area of our community many residents of which are unable to afford a pool at their homes. Other than using the ramadas at Heroes Park or a school cafeteria, the Yucca district continues to have no community meeting location as is found in every other district in the city.

Ever since I returned to the city council in January of 2017 my focus and priority has been to get the library built and the park completed. In 2017 I have achieved some success in getting the library concept approved and funded by city council. I had hoped to see it open as a 2018 Christmas present for Yucca district residents. Alas, although it will be built the timeline continues to slip. Here is the most currently available timeline:

  • 12/4/17                         100% construction drawings submitted to city Building & 
  •                                      Safety Department for review and approval (takes a minimum
  •                                      of 30 days)
  • 1/29/18                         Construction drawings approved for a permit
  • 2/8/18 through 2/15/18  Advertisement for construction bid published
  • 3/7/18                           Bid opening
  • 4/10/18                         Council approval and award of construction contract
  • 5/7/18                           “Notice to Proceed” (NTP) issued to contractor to start work
  • 5/7/18 through 2/7/18     Construction phase (approximately 9 months)
  • 2/7/18                            Possible “Soft Opening”
  • 3/30/18                          Final acceptance by the city of the building 

I will accept some responsibility for the delay for I did not like the original design and requested modifications…some of which were approved. However, I pleaded, begged and stamped my feet to accelerate the process…all to no avail. I’m not sure any sense of urgency was conveyed to the consultant, DFDG, in design of the construction drawings. I question why it takes a month from a 3/7/18 bid opening to bring it to council for approval on 4/10/18. I question why it takes another month (4/10/18 –5/7/18) before the contractor gets a “Notice to Proceed” to actually begin construction.

I am so anxious to get this project underway. I know I am impatient but we have waited so long. I am disappointed that the only one who feels a sense of urgency is me…sigh.  

© Joyce Clark, 2018                 

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.