On Saturday, May 18, 2019 at 9 A.M. the City of Glendale will host the Grand Opening celebration of its newest library branch at Heroes Regional Park located at the northeast corner of 83rd Avenue and Bethany Home Road.

In all honesty, I don’t know whether to laugh or to cry. Why? You’re asking. It should be a day of celebration and it most certainly is. But there is so much more to this happy ending. Let me tell you about it.

Way back in Fiscal Year 1998-99 two projects simultaneously appeared in the city’s Capital Improvement Program (CIP). One was the West Branch Library allocating funds for its design in FY 2001-2002 and its construction was slated to begin in FY 2004. The other was the Multi-Generational Center North allocating funding for FY 2000-2001. The branch library and the multi-gen center were slated to begin in FY 2001-2002.

 In FY 2001-2002 a new major project is added, the Recreation/Aquatics Center North appears. That same Fiscal Year the slippage of just one project, the library, begins. The design of the library is still in FY 2001-2002 but actual construction is moved to FY 2004-2005.

These projects remain constant until Fiscal Year 2003-2004. In 2003-2004 the city experienced some economic difficulties, yet that year, both north projects, the Multi-Gen Center North and the Recreation/Aquatic Center North are approved and merged into one major project for $13,896,012 with a Groundbreaking in April of 2005. The west branch library construction is moved once again…now to Fiscal Year 2005-2006 with an opening in 2007.

Then what do you know? In Fiscal Year 2005-2006 the year that library construction is to begin, a majority of city council moved $6 million in funding for the library to the Glendale Regional Public Safety Training Center construction. Library construction is moved back once again to FY 2008-2009 with an opening in FY 2010. In 2009 the national recession began and I stopped keeping track knowing the city had no money.

To sum it all up, in 8 years the Recreation/Aquatics Center North was open and another 12 years later we are finally opening a branch library in West Glendale. Why? It wasn’t just “economic difficulties.” It was far more than that. The former mayor and I often butted heads on many issues. I was certainly not one of her council “mushrooms.” (Mushrooms are kept in the dark and fed ca-ca.) She and her mushrooms were not about to give “evil” (her nickname for me) a win in my district. As far as I am concerned, it was spiteful retribution. Rest assured she will deny and offer plausible sounding reasons as to why the library was never constructed during her tenure. Consider the source and the motivation.

That is why I could cry. It has taken so bloody long to get this long needed and awaited amenity for the people of West Glendale. An entire generation has grown up without the benefit of a nearby library. That is just not right.

I laugh because the next generation will benefit. Reading must not become a forgotten art. Libraries teach young ones the love of reading and for many it becomes a lifelong habit. For 20 years the Yucca district has been without a public facility in which to hold meetings. Finally the library will have a Community Meeting Room that can be reserved for neighborhood meetings, etc.

Admittedly, the library is tiny at 7,500 square feet but it is not what was first proposed, that of a modular building ( which I considered to be an insult implying that West Glendale residents were not even worthy of a permanent structure) and it is constructed to be expanded. Velma Teague and Foothills are approximately 25,000 to 35,000 square feet and the Main Library is 65,000 square feet. I suspect the pressure of use on this new branch will be so great that expansion will have to occur in a couple of years.

In the meantime there is so much more to be completed at Heroes Regional Park. Projects still to be done include a water feature, a dog park, a Recreation/Aquatics Center West and sports fields – all part of this Park’s Master Plan. I am pleased that there is funding allocated in the upcoming FY 2019-2020 CIP for the water feature. It is the next element of the park that will be constructed.

I guess it’s better to look forward than back but it’s easier to do once one vents and my venting is done. Now I celebrate our new library, soon to be much loved and over used. No longer will we have to wait 15 or 20 minutes at the train tracks just to make a simple trip to the library.

Please join me on May 18th to celebrate. Please bring the kids. Heroes from the Arizona Avengers and Justice League of Arizona will be available for photos. There will be face painting, a balloon artist and a scavenger hunt with prizes for the kids. Adults can check out the new 3D printer, get a library card, use the computers for public use and learn about the Discovery and Exploration Backpack Program. Find out how this library can fit into your family’s fabric of life.

There is also a Heroes Park Brick Walkway Campaign under way. For $100 (individual) to $250 (corporate) one can purchase a brick to be engraved with 4 lines of text. I am placing my order for one this Monday. From the rendering I have seen, it looks like the opportunities to get a commemorative brick in the front entry walkway are limited. I would suggest that you place your order as soon as possible. I don’t know if orders can be placed online but I will find out and update this blog when I do.

So, I will laugh and be joyful. We have a library. Tiny though it might be, it will be mighty in changing the character of the community it serves. For me, it is symbolic of more to come and the completion of Heroes Regional Park after so many years.

© Joyce Clark, 2019         

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

I often find that I no longer have the time to write. I confess I miss not being able to write several times a week. My city council job, which I love, is now a full time but for this evening, I am caught up. I have already done my ‘homework’ for this Tuesday’s city council workshop and voting meeting. That, of course, doesn’t mean that there aren’t things on my ‘to do’ list. I will spend part of this week reading “A Report on EMS Field Experiments” and read the sign codes from Peoria and Surprise in preparation for my Council Business Committee meeting. There is always more to read, more ‘homework’ to do, more events to attend and endless meetings…with council, with staff and with constituents about an issue or developers with another new project to consider.

Right now council is deep in the belly of budget season. Council started its budget meetings in March and just this past week had 2 all day budget meetings. Staff prepared a proposed budget for council’s consideration and we review every element within it. The old adage that “money is power” still rings true in government today whether it’s local government or the federal government. He who controls the purse strings wields the power. Budget is a season of the tug and pulls between staff, continually seeking more funding for its projects or personnel, and that of council with its own set of priorities. It’s never a fierce issue when the economy is bad and there isn’t discretionary funding. When the economy is healthy, as it is now, polite but intense warfare ensues.

One of the priorities for me for the past two years has been the implementation of a dedicated council assistant for each councilmember. For several years the council office has been on a     3-2-1 model meaning that there are 3 council assistants, each of whom staff 2 councilmembers; 2 ‘rovers’, each of whom takes direction (often confusing and without identification of priority) from the 3 council assistants; and 1 secretary.

There is a litany of reasons why this model does not work. One of the results has been that long term projects and research on topics are shelved simply because of the need for a council assistant to meet the daily tasks of the two councilmembers being staffed. Often the council assistant’s work time for each councilmember is uneven as one councilmember’s needs may, and often does, take priority.

This budget year I have requested that the full time employee (FTE) position that council gave up voluntarily last year to partially cover the costs associated with implementing the School Resource Officer (SRO) program be restored. By adding that one FTE, converting the 2 ‘rover’ and 1 secretary position to council assistant positions will finally allow for one council assistant to serve one councilmember. Because of the State Open Meeting Law restrictions I have only been able to discuss this issue with 2 other councilmembers. If I were to talk to 3 councilmembers in a private setting it would constitute a majority of council. It is a violation to establish consensus of the majority without the benefit of a public meeting. The 2 councilmembers with which I have discussed the issue share my belief that we need dedicated council assistants. However, 4 councilmembers are needed to give staff policy direction. I am hopeful that when this issue is discussed at our next budget meeting on April 30th there is a 4th councilmember that will support this initiative.

It’s a delicate dance because by charter, council’s role is policy making and staff’s role is to administer policy and their role includes managing personnel. However, it is within council’s purview to direct senior management, as a matter of policy, to staff each councilmember with an assistant. It then becomes staff’s responsibility to carry out this policy. As salaried employees each council assistant is ultimately managed by the city manager in his role as CEO of all employees within the organization.  

In an acknowledgment of zero based budgeting each year council receives a detailed report on two selected departments. This year it was the Budget and Finance Department and the Information and Technology Department. I find the detail very helpful and informative but I would appreciate it if they were not the last two departments to be discussed at the end of two very long days.

Other things…there are some members if the public that do not like our City Manager, Kevin Phelps. The reasons are many and varied…some reasons may be valid…from their respective perspectives. I do like and appreciate our City Manager. I have served with quite a few…Dr. Martin Vanacour, Ed Beasley, Dick Bowers, Interim Horatio Skeete and now Kevin Phelps. The only one with which I never served is Brenda Fischer and for that I am extremely grateful. The one who stands out above all is Marty Vanacour but Kevin Phelps runs a close second. No one is perfect…certainly not me…and certainly not any of Glendale’s City Managers. Kevin Phelps took a city on the verge of bankruptcy and implemented policies that have made Glendale financially healthy once again. He is a man driven to make Glendale prosper and to make it a vibrant job center for Glendale residents. Along the way he has had a few missteps but generally he has been good for Glendale.

His past experience in Washington State includes running a major convention center, experience as an auditor as well as experience as an appointed and elected official. He retains my vote of confidence and I hope he will stay on for several more years and continue to ‘make Glendale great again’.

The West Branch Library at Heroes Park at the northeast corner of 83rd Avenue and Bethany Home Road is nearly ready to open. Look for it to open to the public in mid-May. As soon as the date for the Grand Opening is finalized I will announce it on social media. It’s been 20 years since the branch library first appeared in Glendale’s Capital Improvement Program (CIP). An entire generation of children in the Yucca district has grown up without the benefit of a nearby library.  I have no doubt that this branch library will be extremely popular and statistics about its use will far surpass any staff estimates.

Library staff will start preparing for the opening by having library furniture and shelving delivered today. The digital sign at the park alongside 83rd Avenue funded from my city council budget (taxpayer funds) has been installed and is functional. The first major message that the public will see on the sign will be the announcement of the library’s grand opening date. It will be used to announce district and city-wide events. Look for a Yucca district meeting to be held at the library toward the end of May or beginning of June. The date of the Yucca district meeting will be advertised on our new digital sign.

The next Heroes Park element to be developed is the water feature. Funding is secured (once the budget is approved) for the design of the water feature. It is my intent to request funding for its construction in the following fiscal year. There is still much to be done at the park but by taking one bite of the apple at a time, I have no doubt it will be completed.

So much is happening in Glendale and most of it is positive. While the economy is good and we reconstitute our rainy day fund, there are opportunities to not only bring new amenities to Glendale’s residents but to improve the look and feel of Glendale (neglected for years because of a poor economy). Glendale is on the move! Look for more great  things in its future and yours.

© Joyce Clark, 2019         

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

I find as City Council responsibilities increase year over year finding the time to write a blog becomes more difficult. I have no intention of giving it up but you may find that, alas, my entries are more infrequent. This morning I discovered that I had a couple of hours free to devote to writing a catch up blog. Y-e-a-a-a!

I am sure, if you are a Glendale resident, you have seen the “Birds” (motorized scooters) suddenly and without warning descend upon our city. Glendale is not the only city to deal with this issue. It is occurring nation-wide from Durham, North Carolina to Los Angeles, California. Apparently these motorized scooter providers (Bird is not the only company) have recognized that most cities have no laws prohibiting them and so, they felt free to drop them in mass quantities wherever they chose.

Late last week, the City of Glendale, sent Bird a Cease and Desist Letter advising the company that their scooters were illegally operating on the city’s rights-of-way, roadways and sidewalks. The company was instructed to pick them up or face a fine of $250 per scooter per hour. Expect all of them to disappear in the very near future. The latest work is that they should be gone by February 9th. As suddenly as they appeared they should disappear. City Council and staff will take the time necessary to decide if scooters are acceptable in our community and if so, what regulations will be required.

Glendale is booming. Look for announcements over the next few months about some major projects, most of which will be located in the Yucca district which I represent. Development plans that have lain dormant since the Great Recession are being dusted off, updated and actively pursued. Many of them include an office development component and will be located in the Yucca district. Glendale simply has no available office space left as of this date but potential development submittals could create as much as a million square feet of office space over the next year and a half. That is welcome news because available office space means more job opportunities for Glendale’s residents.

City Council had approved the annexation of the Woolf Logistics and Lincoln Logistics parcels located just east of the Loop 303. The developers of both parcels are actively marketing to distribution and manufacturing companies. I am confident we will see both of these developers selling off parcels for active development this year. This is exactly what Glendale has been pursuing. Residential development is fine in certain areas where there is existent infrastructure but each home costs the city about $400 annually. That is because the tax generated…sales, property taxes, etc…do not generate enough to cover the entire costs of public safety, street maintenance and other services that a city must pay to provide those services. Manufacturing, office and distribution do pay for themselves annually and have the additional benefit of job creation. City Council’s goal is to develop land adjacent to the Loop 303 for those uses. In the future Glendale may be able to reverse the current data that shows that 70% of our residents go outside of Glendale to go to work.

Next week, the first week of February, city council begins to hold budget workshops in preparation for the final adoption of the FY 20-21 budget this coming June. It has been said and it is true, there is never much in-fighting when the available funds are lean but whenever there is a surplus the in-fighting increases. Glendale has an available surplus of about a million dollars this year. There are so many needs, long overdue, that require funding. One of the most critical for me is to continue to complete Heroes Park. It has been 20 years since the first project was completed in this park. This spring we will see completion of the construction of Phase I of the West Branch library in Heroes Park. I commend the city council for recognizing this critical need and allocating the funding to make it happen. However, Heroes Park is far from complete. It still does not have a water feature, a recreation and aquatics center, ball fields, library expansion or a dog park. These were elements of the original plan and still an expectation of the thousands of residents surrounding this park. They have seen their children grow up without the benefit of many elements in this park and now have the expectation that their grandchildren will finally have a completed park nearby.

Another project long overdue is that of O’Neil Park’s inoperable swimming pool. The square mile, primarily a low socio-demographic area, surrounding this park has over 1300 homes and 10 apartment complexes. That equates to a lot of children without an active recreational opportunity. For the past 5 years the O’Neil pool has been closed. It’s time to rehabilitate O’Neil Park and to provide some active recreational opportunities for the estimated 4,000 children living in this area. While the pool may disappear there are plenty of possibilities for that space within the park that can become a positive benefit to the area’s children.

I hope that I will soon be able to blog about some of the exciting new projects coming to Glendale. They are in the pipeline but not yet finalized for announcement. I am very optimistic about Glendale’s opportunities for the coming year. The economy is healthy and spurring new development everywhere and Glendale intends to capture its share.

© Joyce Clark, 2019         

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

News headline announcing my candidacy several years ago

It’s Saturday afternoon and this morning I participated in the Third Annual Glendale Hometown Parade. I rode in a beautiful vintage blue Cadillac convertible. What a treat. This afternoon I should be baking Christmas cookies or doing my ‘homework’ in preparation for Council’s Strategic Policy Workshop this Monday or Tuesday’s Council Workshop meeting and subsequent evening voting meeting. I will do all of those things tomorrow. Instead, after nearly 2 years of serving as Glendale’s Yucca District Councilmember, I spent the afternoon reflecting about the past two years of my service and what my future should be.

When I began this current term I announced it would be my last. I assumed, incorrectly, that after 4 years of service I would experience diminishing capacity, physically and mentally. That has not happened. Every year I get my executive physical and each time I pass with flying colors. There has been no erosion of either my physical or mental capacities to do the job that you elected me to do.

I am announcing today that I will run for another term.

I have won some issues and lost some. I am most gratified that I have secured recognition for and a commitment to complete Heroes Park. I secured funding for the West Branch Library at Heroes Park and it is currently under construction and scheduled to open late March or mid-April of next year (2019). It is my intent to hold my next district-wide meeting at the newly opened library.

I do not intend to stop there. I plan to secure funding for the design of the lake feature in Heroes Park in our upcoming FY19-20 budget and to secure funding for its construction in the following FY 20-21 budget. After that there are still the ball fields, recreation center and library expansion to complete. Those are my goals.

I am proud to have gotten support of the entire council to start LED street light conversion immediately. That action saves the city about $700,000 in annual operating and maintenance costs for our street lights and results in an annual electrical rebate of nearly half a million dollars.

I am also proud of council’s approval of my initiative to start a Council Subcommittee on Business. The committee recently reviewed staff’s suggested amendments to the plumbing, electrical and fire codes resulting in the committee’s recommendations to delete or modify certain provisions all of which received acceptance from the entire city council. There is still more work to be done but the committee is making progress toward the goal of making Glendale more business friendly.

Council approved my request to use modified ‘Zero Based Budgeting’ to review selected departments during Council’s annual building of the city’s budget. This year it will be applied to the IT (technology) department and the Finance Department. It is a method of budget review that can result in greater fiscal efficiency.

My greatest disappointment has been a majority of council’s approval of the amended Stonehaven residential project located from Bethany to Camelback and 83rd to 91st  Avenues. The approval by a majority of council for small lot sizes of 3,000 and 3,500 to be located north of Camelback is clearly detrimental to all those who live adjacent to or near this planned development.

Perhaps the only good to come out of this project will be at the start of the project’s development — Bethany Home Road between 83rd and 91st Avenues will be constructed. That may help to alleviate some of the tremendous traffic we experience on Camelback Road. In the next 2 years Camelback between 91st Avenue and the Loop 101 will be redesigned and reconstructed to mitigate (as much as possible) the traffic in that area.

There is still much to do to advance the interests of our district and the city. Two areas of concern are the performance of the city’s code department and continued pressure to develop vacant, infill parcels in the district.

I am pleased that I will be serving on the newly created Code Compliance Committee and look forward helping to improve the code department’s poor and inconsistent performance seen in so many parts of Glendale.

 Land development is oft times a harder nut to crack. If a property owner sells a piece of land and the developer builds to the current property’s zoning it is impossible to stop that private commerce. However, I have been successful in gaining many developers’ agreement (which does not have to be granted) to build mixed sized projects that include not just standard lot sizes but larger lot sizes within their projects.

There is much to be done to keep Glendale and the Yucca District moving forward in a positive direction. I am thankful that I have had an opportunity to shape policy thus far and look forward to continuing to make both the best they can be.

I will establish a political action committee (PAC) in January of 2019 and begin fund raising for the campaign ahead. I ask for your support by donating to my campaign or volunteering to help me as I walk neighborhoods. As I move forward I will establish a secure method of online donation.  I am always available for small neighborhood or HOA meetings. Just call and I will be there.

I would appreciate seeing your comments regarding my announcement. Thank you for the opportunity to serve you and to represent you. It has been and continues to be my honor and privilege. I will continue to do the very best job that I can.

© Joyce Clark, 2018         

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

 

[poll id=”29″]Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

First let me recognize and thank this city council for approving Phase I of a permanent West Branch Library currently under construction. However, Heroes Park is far from complete. It’s a twenty year commitment by Glendale still not met. Heroes Park still lacks its Recreation & Aquatics Center (a la Foothills), its water feature, a dog park, a Phase II expansion of the library and its ball/soccer fields.

Heroes Park Concept Plan

 

 

 

 It drives me nuts when I pick up the paper and read that Phoenix will invest between $80 and $100 million to upgrade Margaret T. Hance Park (also known as the “Deck Park”) to include a jogging loop, a skate park, a splash pad area, enhancements to its events area and more trees for shade. Or that Avondale will spend $12 million to upgrade its Festival Fields Park with a lake, dog park, splash pad, ramadas, new lighting, restroom and playground equipment replacement and volleyball, pickleball and basketball courts. Or that Goodyear is investing in a 30-acre park with a recreation center and an outdoor aquatic facility.

I accept that Glendale faced enormous fiscal adversity and the decisions of the current councilmembers and mayor were critical in reversing those problems. I accept that Glendale, as every other city, weathered the Great Recession. But now Glendale is facing a bright financial future and the completion of this park is a moral debt owed to the citizens of south and west Glendale.

They have waited for 20 years…marking a full generation of children that never had the opportunity to use Heroes Park. This is a city council promise that must be fulfilled for all of the people that bought homes in the area on the reliance that there would be a park nearby.

What angers south and west residents is that Foothills Recreation & Aquatics Center was placed into the city’s Capital Improvement Plan (CIP) in Fiscal Year 98-99 (the same year as Heroes Park) as a Multi-General Center North and in addition in Fiscal Year 01-02 a Recreation & Aquatics Center was also added. In Fiscal Year 03-04 both projects were merged into the Foothills Recreation & Aquatics Center. Groundbreaking occurred in 2005 with completion of the project in 2006. It took 7 years from identification in the CIP until it was opened for business. And yet Heroes Park remains in large swaths of dust, dirt and weeds. It is not only an eye sore but an embarrassment to all.

Until this park is completed with all of the elements of its master plan, people will continue to believe in a sentiment I have heard expressed often and bitterly. They point to Foothills with its library and recreation & aquatics center and say, north Glendale is placed before the rest of Glendale and there is some truth to that belief.

In the 1980’s the Hunt brothers had acquired most of the land known today as the Arrowhead area. Their plans were to develop a master planned residential community. However, the brothers attempted to corner the silver market resulting in their bankruptcy. The leaders of Glendale at that time made a commitment to save the dream of Arrowhead pouring at least $70 million into the area to guarantee its development. Their action saved Arrowhead but at what cost? Dollars that would have been used throughout Glendale were instead diverted to Arrowhead. For several years Glendale’s financial resources were targeted up north while the rest of the city’s needs were unanswered. That well intentioned action caused tremendous citizen resentment that persists to this day.

Sometimes that resentment becomes exacerbated when over 1,000 citizens sign a petition to moderate the proposed Stonehaven residential project and their voices are ignored or when O’Neil Pool, waterless and no longer useable remains a gaping scar for years within O’Neil Park. People shrug their shoulders with a palpable sense of embitterment and defeatism.

Fixing the O’Neil Pool problem and completing Heroes Park will go a long way to restoring peoples’ faith that the city will treat all of its areas with some sense of equity. No longer would south and west residents have cause to believe that they are step children, often ignored.

Everyone acknowledges that these promises – Heroes Park and O’Neil Pool — were not made on the current senior management’s or council’s watch but now that Glendale is back on track financially it is incumbent upon them to finally fulfill these promises. These two projects will restore a sense of pride in their city for south and west Glendale residents.

Every district within Glendale has its “Points of Pride,” those recreational amenities created for the use of our residents.  

  • Cholla district has the Foothills Library, the Foothills Recreation & Aquatics Center and Thunderbird Conservation Park.
  • Sahuaro district is proud of its Paseo Racquet Center & Park; Skunk Creek Park and Thunderbird Paseo Park.
  • The Barrel district can point to the Adult Center, the Main Library and Sahuaro Ranch Park.
  • The Cactus district residents enjoy the Elsie McCarthy Sensory Garden, the Rose Lane Aquatics Center and Manistee Ranch.
  • The Ocotillo district claims the Velma Teague Library, the Civic Center and Murphy Park & Amphitheatre.
  • The Yucca district has the Grand Canal Linear Park and …???? An unfinished Heroes Park.

When will our promise be fulfilled?

© Joyce Clark, 2018         

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

First a little history. Twenty years ago, in 1998, what is today known as Heroes Park first appeared in the city’s Capital Improvement Program (CIP). Today Heroes Park remains unfinished…after 20 years of waiting. Residents who bought in this area expected its timely completion. Instead they raised a generation of children without the benefit of this quality of life amenity, especially a library.  Now they have grandchildren whom they hope will be able to enjoy a completed park before they too become adults with their own children.

Heroes Park Concept Plan. Items depicted in yellow are completed. All others have not.

One of the planned components of the park has always been a West Branch Library. Again, more history. The former mayor (Scruggs) used every ploy to deny funding for the library and park completion. She and I butted heads on virtually every issue and she was not about to give the person (whose nickname for me was “Evil”) any kind of victory – especially a park, rec center and library. Her most infamous raid occurred in 2006 when she and her “mushrooms” (the gang of four whom always did her bidding) diverted $6 million dollars from library construction and allocated it to the construction of the Glendale Public Safety Training facility (GRPSTC). The result being funding for library construction vanished in an instant.

When the great recession occurred every possible residential amenity was cut from the CIP including completion of Heroes park, rec center and library. These were not the only amenities to get the axe. Library hours were cut and many youth recreation programs disappeared or were severely diminished. O’Neil Pool in the Ocotillo district (formerly part of my district, the Yucca district) received no funding during that period after it was closed due to the need for major repairs. To this day it remains closed and in need of significant funding to repair or replace it. It is a disgrace.

Over the past 20 years south and west Glendale often were ignored when it came to allocating city funding for amenities with one exception – Rose Lane Aquatic Center, in the Ocotillo district, was constructed. To this day it is heavily used by an economically challenged area of our community many residents of which are unable to afford a pool at their homes. Other than using the ramadas at Heroes Park or a school cafeteria, the Yucca district continues to have no community meeting location as is found in every other district in the city.

Ever since I returned to the city council in January of 2017 my focus and priority has been to get the library built and the park completed. In 2017 I have achieved some success in getting the library concept approved and funded by city council. I had hoped to see it open as a 2018 Christmas present for Yucca district residents. Alas, although it will be built the timeline continues to slip. Here is the most currently available timeline:

  • 12/4/17                         100% construction drawings submitted to city Building & 
  •                                      Safety Department for review and approval (takes a minimum
  •                                      of 30 days)
  • 1/29/18                         Construction drawings approved for a permit
  • 2/8/18 through 2/15/18  Advertisement for construction bid published
  • 3/7/18                           Bid opening
  • 4/10/18                         Council approval and award of construction contract
  • 5/7/18                           “Notice to Proceed” (NTP) issued to contractor to start work
  • 5/7/18 through 2/7/18     Construction phase (approximately 9 months)
  • 2/7/18                            Possible “Soft Opening”
  • 3/30/18                          Final acceptance by the city of the building 

I will accept some responsibility for the delay for I did not like the original design and requested modifications…some of which were approved. However, I pleaded, begged and stamped my feet to accelerate the process…all to no avail. I’m not sure any sense of urgency was conveyed to the consultant, DFDG, in design of the construction drawings. I question why it takes a month from a 3/7/18 bid opening to bring it to council for approval on 4/10/18. I question why it takes another month (4/10/18 –5/7/18) before the contractor gets a “Notice to Proceed” to actually begin construction.

I am so anxious to get this project underway. I know I am impatient but we have waited so long. I am disappointed that the only one who feels a sense of urgency is me…sigh.  

© Joyce Clark, 2018                 

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

I thought it was only mainstream media that indulged in fake news…but now it looks like our local paper has joined the parade. Well, perhaps it’s not fake news but the headline and article are certainly misleading. The headline reads, Heroes Regional Park Library costs rising. It implies that the West Branch Library costs are too expensive to merit its construction. Here is the link: http://www.glendalestar.com/news/article_61165fb2-a7c2-11e7-b123-9fc4a27d9987.html .

The initial estimate for construction of the West Branch library has been elusive from the start. The $2.7 million dollar figure used by Director Erik Strunk in 2016 was no more than an educated guesstimate as no design work had been done when this item came before city council in a May 5, 2016 workshop. Here is the link: https://www.glendaleaz.com/clerk/agendasandminutes/documents/2016/0405/Minutes.pdf .

The original estimate did not include technology or underground infrastructure costs. The increase now accounts for those costs.

While it is entirely appropriate to offer an explanation of why construction costs for the West Branch library have increased by over a million dollars, the tone of the article seems to question why an increase is merited for this library branch. It’s almost as if the underlying question is the worthiness of such an increase in our part of town. The implication being do we deserve it?

Perhaps a little history is in order. In April of 1997, twenty years ago, staff brought forward an estimated cost to build the Foothills Library branch of $5.1 million. A year later, in the city’s Fiscal Year 1998-99 Budget book the cost had risen to $6.3 million, an increase of $1.2 million. There was no Glendale Star article questioning that increase…after all, it was for the Arrowhead area, you know. Also keep in mind, the Foothills Library branch at $6.3 million was in dollars of twenty years ago. Obviously, inflation and the rising cost of everything should be considered when considering the cost estimate for the West Branch library.

In Fiscal Year 2008-09 nearly $7 million was budgeted for the West Branch library. That amount was budgeted after a majority of council in Fiscal Year 2006 had diverted $6 million for the library to the Public Safety Training Center.

Then there is the issue raised of modular versus a brick and mortar building. Previously Director Strunk indicated that the costs of either modular or brick and mortar were comparable. Ever since west area Glendale residents heard of the possible modular building they have been vehemently opposed. They were insulted that the city thought so little of them that all they deserved was a temporary modular building. They insisted on brick and mortar. They conveyed this sentiment to staff at every opportunity.

It’s also important to note that recently I received a call from a Glendale resident who asked to remain anonymous, as he worked in the modular building industry for over 30 years. If anyone should know about modular buildings it would be this person. He wanted me to know how pleased he was, after viewing a recent council workshop discussion on the issue, that the city was pursuing brick and mortar construction. He said that modular constructed buildings simply do not last beyond about 7 to 8 years, at which time they begin to deteriorate. He felt that something as important as a city library merited hard construction and that it would be a structure lasting far longer than anything in the modular industry. He also said that special construction of a modular designed to be expandable increased ordinary modular construction costs considerably.

It is also instructive to include some of the discussion that occurred at the April 5, 2016 council workshop. Here are just two excerpts of note:

“Councilmember Aldama asked if it would be the intent to build onto this facility in the future.

Mr. Strunk said they asked this project to be designed to allow future expansion and growth.  The design will accommodate that growth.  He explained the vision for this project is a 33,500 square foot library.

Councilmember Aldama asked if the initial project was considered Phase 1 and if a funding mechanism would be put in place to ensure completion of this project.

Mr. Strunk said he would await Council direction on that issue, but park facilities have been phased in before.”

And this, “Councilmember Malnar said the $2.7 million was being taken away from providing additional services at other Glendale libraries.  He asked if the city was losing more than they were gaining by using those funds to build another library.

Mr. Strunk said the $2.7 million is development impact fee money was specifically collected for a library.  They can be used to construct, equip, build and open a new library.  They cannot be used for operating funds. “

The topic concluded with the following, “Mayor Weiers said there is a consensus to continue on with this project. Mr. Strunk asked if consensus meant to commence design work on the Heroes Park concept. Mayor Weiers said that is the next step.”

Let’s acknowledge that the West Branch library has been in the city’s Capital Improvement Program (CIP) since 1998…going on twenty years. Let’s also acknowledge that during the 20 year reign of the previous mayor it was never destined to be built. Roadblocks were manufactured at every turn to prevent its construction.

It’s time for everyone, including the Glendale Star, to stop sniveling about a major infrastructure project, the West Branch library, and the worthiness of its construction in west Glendale. Instead, it’s time to rejoice in the fact that due to its economic recovery, the city has finally made good on a twenty year old promise…long overdue.

© Joyce Clark, 2017                 

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

Tonight, April 20, 2017 residents of the Yucca district will have an opportunity to meet Glendale’s City Manager, Kevin Phelps and Glendale’s Police Chief, Richard St. John.

There will also be a presentation of concept designs prepared by the Dick & Fritche Design Group for the West Branch Library to be located at Heroes Park, 83rd Avenue and Bethany Home Road. Residents will have an opportunity to comment on the conceptual designs.

As is my usual agenda, the final half hour will be an Open Forum providing residents an opportunity to comment on issues and concerns.

There will be a drawing at the end of the evening for 2 free tickets to the Zac Brown Band concert, May 4th, at the Gila River Arena. Must be 18 years of age and a Yucca district resident to be eligible.

Light Refreshments will be served. All are welcome. It doesn’t matter where you live in Glendale for it’s an opportunity to learn about Glendale’s issues.

© Joyce Clark, 2017              

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

Disclaimer: The comments in this blog are my personal opinion and may or may not reflect an adopted position of the city of Glendale and its city council.

Whew, It’s been a rough two weeks (since April 5th) with my blog site being down. My thanks to all of you who have patiently waited for its resurrection. I did lose some posts that occurred between March 11, 2017 and today. Thanks to the Word Press team and especially my genious grandson (majoring in IT) for solving the Gordion Knot of computer software enabling me to post once again. I know I will be throwing some money in my Grandson’s direction for saving my site.

What’s been happening in the meantime? On Tuesday, April 4, 2017 city council had another Budget Workshop meeting. Mostly it reaffirmed suggestions made by council at the previous budget workshop. One of my “asks” at the previous workshop was to consider moving up the proposal to transition the city’s street light system city-wide to LED lighting. This project would result in cost savings to the city of a half million dollars a year that could be redirected to providing greater dollar capacity to repair and maintain even more city streets annually. Council was presented further information and approved moving the project forward in the coming Fiscal Year rather than waiting until Fiscal Year 2023.

I was also successful in getting Heroes Park and O’Neal Pool back into the Capital Improvement Program. This is but a first step. If these items are not even listed in the CIP, it is impossible to secure funding for them.

Previously I had asked for consideration of returning funding to an upgrade of Pasadena Park that was pulled in favor of a new project, construction of a bike path at Foothills Park. I pointed out that council identified priorities were to maintain and improve existing assets before creating new projects. At that time Councilmember Lauren Tolmachoff seemed to agree with that premise and was amenable to removing the new bike path project. On the April 4th budget meeting she seems to have reversed her position and now is reluctant to give up this new project. As many residents down our way are fond of saying quite often to me, “Them that has, gets more. Them that has nothing, gets nothing.”

The next several council budget workshops will deal with individual departments and their budgets. I am sure I will have questions…lots of questions. That’s one good aspect of having 16 years worth of historical memory…it helps me to identify in which areas of the city to take a good, long look.

On Friday, April 7th, I went down to the studios of Channel 3 TV for the taping of a segment for a show called Politics Unplugged. Here is a link:  https://www.youtube.com/watch?v=PTAoX-SiS6Y&feature=youtu.be . The segment was about local fire unions’ influence in elections and followed on the heels of an Arizona Republic story on the same topic. Here is the link to the Arizona Republic article: http://www.azcentral.com/story/news/local/arizona-investigations/2017/03/28/arizona-firefighter-unions-donated-hundreds-thousands-local-elections/99603914/ .

There are a few more events about which I would like you to be aware. One is a neighborhood public meeting to learn about a proposed residential project to be sited at the southeast corner of 83rd Avenue and Northern Avenue. It will be on Thursday, April 13, 2017 at 6 PM at the Harvest Church, 8340 W. Northern Avenue. The applicant is seeking to place 50+ homes on 6,000 square foot lots…ugh.

On Thursday, April 20, 2017 at 6 PM I will be hosting another Yucca district meeting at the Coyote Ridge Elementary School Cafeteria, 7677 W. Bethany Home Road. Residents will have an opportunity to meet and to hear from our new City Manager, Kevin Phelps, and our new Police Chief, Richard St. John. They will stay for the entire meeting so that residents may introduce themselves and ask questions.

After those two speakers, there will be an informal meeting of the Parks & Recreation Board and the Library Advisory Board for the purpose of hearing a presentation from the Dick & Fritche architectural firm on a proposed design concept for our West Branch Library.

Following that presentation, as is normal for my district meetings, I will open the floor for residents to comment on the proposed library or any other topic. At the end of the formal meeting, please take the time to meet our City Manager and Police Chief.

© Joyce Clark, 2017               

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.

As readers of this blog know I have been opposed to the idea of a temporary modular building (trailer) as our west branch library in Heroes Park. I and many, many residents of the Yucca district consider this an insult, as if that is all that we deserve after waiting 18 years.

After the city council acceptance of the Canvass of Votes I was invited to meet on October 7, 2016, with appropriate city personnel regarding the plans for this library. I had requested a meeting after it came to my attention that approximately $2 million dollars would be available for its construction and it appeared that the cost to build a permanent, phase I of a brick ‘n’ mortar branch library would be virtually the same as the cost of a modular building. My meeting with city staff confirmed that $2 million dollars would be sufficient for either a brick & mortar building or a modular building.

Based upon that information and learning that the next step would be to secure city council approval to move forward with the design, I requested that the design process incorporate plans for a permanent brick & mortar building as well as the modular design. The modular design had been directed by city council in a previous action.

I was successful in getting the design for a permanent brick & mortar included in the proposed city council action and on December 20, 2016, city council authorized the City Manager to enter into a Professional Services Agreement with Dick and Fritsche Design Group, Inc. (DFDG) to provide design and architectural drawings for the potential Heroes Branch Library, within Heroes Regional Park located at West Bethany Home Road and North 83rd Avenue, in an amount not to exceed $410,090. Here is the link to that city council meeting: http://glendale-az.granicus.com/MediaPlayer.php?view_id=2&clip_id=2597&meta_id=55164 .

Below is the schedule of work.  As can be seen, it will be 9 months to create the design and construction documents. Although that seems to be very slow, in city terms, it is fast and being expedited. I will monitor the progress of the various steps to make sure the timeline remains intact. The next milestone will be for city council to award a construction contract to build in approximately September of 2017. I will continue to advocate for and seek acceptance from council for the permanent brick & mortar west branch library building. Knowing that the costs are virtually the same for either type of building it would make economic sense that a permanent structure be built with the capacity for future expansion. The library itself will be completed and open for business approximately August of 2018.

·       Notice to Proceed                                                                        1/2/17  

·       Program Verification – Site Analysis                                          1/2/17-1/13/17 (2 weeks)

·       Schematic Design                                                                         1/16/17-2/24/17 (6 weeks)

·       Design Development                                                                   2/27/17-4/21/17 (8 weeks)

·       Construction Documents                                                            3/1/17-3/31/17, 4/24/17-6/16/17

                                                                                                                (8 wks.)

·       Plan Review and Permit / Prepare Bid Docs.                            6/19/17-8/11/17   (8 weeks)

·       Bid                                                                                                    8/14/17-9/8/17 (4 weeks)

·       Notice to Proceed                                                                         9/11/17-10/20/17   (6 weeks)

·       Council Award                                                                                10/12/17 

·       Construction                                                                                   10/23/17-7/27/18 (40 weeks)

·       Close out – Occupy                                                                         7/30/18-8/24/18 (4 weeks)

·       Final Acceptance                                                                            8/27/18

I will also continue to advocate for additional elements of Heroes Park, also long overdue. Nearly every district has its points of pride from the Foothills Library and Foothills Recreation & Aquatic Center, to Sahuaro Ranch, to Thunderbird Paseo Racquet Center, to Murphy Park and the Civic Center. It’s time for west Glendale to have its major amenity and its point of pride completed.

© Joyce Clark, 2016        

FAIR USE NOTICE

This site contains copyrighted material the use of which is in accordance with Title 17 U.S. C., Section 107. The ‘fair use’ of any such copyrighted material as provided for in Section 107 of the US Copyright Law and who have expressed a prior interest in receiving the included information for research and educational purposes. For more information material on this site is distributed without profit to those who have not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democratic, scientific and social justice issues, etc. We believe this constitutes a ‘fair use’ of any such material. For more information go to http://www.law.cornell.edu/uscode/17/107.shtml. If you wish to use copyrighted material from this site for purposes of your own that go beyond ‘fair use,’ you must obtain permission from the copyright owner.